AIM: A 100 m WBM road needs to be constructed inside the Skill Lync Education center premises to allow access to the center for students and faculties.Create the following Project (under same EPS/OBS as project-1) and Resource :Project Name - Education Centre RoadAssume - Calendar as 6 x 24 and start date on 22nd Feb 2021…
Sanjay Jagadeshwara E
updated on 04 May 2023
AIM:
A 100 m WBM road needs to be constructed inside the Skill Lync Education center premises to allow access to the center for students and faculties.
Create the following Project (under same EPS/OBS as project-1) and Resource :
Project Name - Education Centre Road
Assume - Calendar as 6 x 24 and start date on 22nd Feb 2021
Procedure :
*Open the previous project in P6
*Go to projects page > new project
*Choose eps as previous " Skill-Lync education "
*name the project as Education Centre Road
*Mention the start date as 22nd Feb 2021
*Calendar as 6X24, and choose the responsible manager
*Go to enterprise tab >resources option
*Click +
*Name the resources accordingly as given in the question
The same is done for the rest 2
*Adding activities > go-to activities select ECR project
*Click +
*add the activities according to the question
*duration is added
*now the predecessors are added
2. Use 3-Tier timescale with Year / Month / Weeks
4. Add a budget to your project - INR 6 cr.
*Go to budget log and add in the details
5. Assign a baseline to the project
Go to project>maintain baseline
Again go to project >assign baseline
6. Add following expense:
Task - 1 - Rs 20,000/- (Item - Fuel)
Task - 2 - Rs 30,000 /- (Item - Maintenance)
*project >enpense option
*Click +
*select the activity and add the details accordingly to the question
7. Generate material resource costs curve
8. Generate an activity-wise cost report
*Report >+
*New report >activities >relative subjects
9. Create a reflection
Go to project page > right -click >select reflection
10. In the reflection, auto update the project at 15 days from start
*right click the reflection project
*open project
*Change date to 15 days ahead the current project
11. Open a TSLD view of the project in Visualizer
*Tools >Visualizer option
*Click + > TSLD > ECR project >okay
12. Add curtains up-to first 15 days of the project.
*Right -click on the left side project page >attachments >curtains
3. Find out the actual cost for labour, non-labour and material cost of the updated schedule
*Go to project page > calculation tab
*select actual to Remaining
*Select resources to find the value
Leave a comment
Thanks for choosing to leave a comment. Please keep in mind that all the comments are moderated as per our comment policy, and your email will not be published for privacy reasons. Please leave a personal & meaningful conversation.
Other comments...
Project 2
AIM: A 100 m WBM road needs to be constructed inside the Skill Lync Education center premises to allow access to the center for students and faculties.Create the following Project (under same EPS/OBS as project-1) and Resource :Project Name - Education Centre RoadAssume - Calendar as 6 x 24 and start date on 22nd Feb 2021…
04 May 2023 11:54 AM IST
Project 1
Step 1: Make the EPS as “Skill-Lync Education” and OBS and assign a Project Manager * Enterprise tab > OBS > add ( new > project manager ) *Enterprise > EPS >Skill -Lync education *Assign > OBS ( project manager ) *Click okay project us created under EPS " Skill-Lync Education Centre" *Project will start on 1st October…
25 Apr 2023 03:50 AM IST
Project 2
1. Design a Warehouse Building located in Chennai using STAAD Pro Connect Edition. The specification must be as follows: Width 30m Length 50m Eave Height 9m Bay spacing 6m Soil type Medium Safe Bearing Capacity 200 kN/m2 Roof slope 1 in 12 Assume suitable sections for structural elements. Follow IS800:2007, IS1893…
12 Apr 2023 07:33 AM IST
Week 12 Challenge
Design of Foundation in STAAD Foundation 1. Isolated Footing Design isolated footing for a column 300 mm x 450 mm, carrying axial load of 1500 kN and Mu = 150 kNm using STAAD. Foundation. Assume that the moment is reversible. The safe bearing capacity of the soil is 200 kN/m2 at a depth of 1 metre from ground level. Use…
10 Apr 2023 12:38 PM IST